Khoemacau Copper Mine

An underground copper and silver mine in Botswana's Kalahari Copperbelt, being expanded to more than double its output.

Explainer film in production
§ 01About the project

Khoemacau is an underground copper-silver mine in the Kalahari Copperbelt of north-western Botswana. China's MMG bought the mine in March 2024 for an enterprise value of about US$1.875 billion and later brought in a partner, CNIC Corporation, which holds 45%. In December 2025 MMG approved an expansion of about US$900 million that adds a new 4.5 million-tonne-a-year processing plant and new mining areas, raising capacity to about 130,000 tonnes of copper a year. Construction began in early 2026, with first concentrate from the expansion expected in the first half of 2028.

§ 02What it aims to do
  1. 01Raise annual capacity to about 130,000 tonnes of copper in concentrate, with more than 4 million ounces of silver
  2. 02Bring the Zone 5 North, Mango and Zeta North-East deposits into production
  3. 03Lower unit costs as output grows
  4. 04Explore the potential for up to 200,000 tonnes of copper a year
  5. 05Build Botswana into a significant copper producer alongside its diamond industry
§ 03Milestones
  1. 2021 · completed

    Production Start

    The mine began producing copper-silver concentrate from its Zone 5 underground operation.

  2. 2024 · completed

    MMG Acquisition

    MMG completed its purchase of the mine in March 2024 at an enterprise value of about US$1.875 billion.

  3. 2024 · completed

    CNIC Partnership

    MMG reduced its holding to 55% after CNIC Corporation subscribed for a 45% stake.

  4. 2025 · completed

    Expansion Approved

    MMG approved a feasibility study and an expansion of about US$900 million to 130,000 tonnes of copper a year.

  5. 2026 · in progress

    Construction Begins

    Ground was broken on the expansion; 2026 output guidance is 48,000-53,000 tonnes of copper.

  6. 2028 · upcoming

    First Expansion Concentrate

    First concentrate from the new plant is expected in the first half of 2028.

§ 04Engineering & resources

Mineral Resource

Copper-Silver Deposits

Sediment-hosted copper-silver deposits including Zone 5, Zone 5 North, Mango and Zeta North-East.

Processing Plant

New Process Plant

A 4.5 million-tonne-a-year concentrator under construction as part of the expansion.

Financing

Expansion Funding

Capital cost of about US$900 million (MMG's feasibility figure is US$936 million).

Project Owner

Joint Venture

MMG (55%) and CNIC Corporation (45%).

  • Underground long-hole open stoping
  • Conventional crushing, grinding and flotation to copper-silver concentrate
  • New 4.5 Mtpa process plant (under construction)
  • Road transport of concentrate to regional ports

What it means for the community

Khoemacau is helping Botswana build a copper industry in a country long defined by diamonds, at a time when diamond revenues have fallen. The expansion should create construction jobs and longer-term mining employment in a sparsely populated part of the Kalahari, though water, power and road transport to export ports remain practical constraints.

§ 05Articles

No articles on this project yet. Subscribe to the newsletter to hear when one is published.

§ 06Partners & owners
  • MMG (55%)
  • CNIC Corporation (45%)